In an ongoing effort to provide quality wireless service, T-Mobile has identified your community as one that will benefit from improved network coverage.
Milestone Communications is proposing a wireless telecommunications facility at Fauquier High School, addressed 705 Waterloo Road, Warrenton, VA 20186.
The proposal is for a 130-foot monopole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. T-Mobile will be the first wireless carrier to locate on the proposed tower.
Please continue to visit this site for updates!
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
Special Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.
Conduct Bid Walk With Contractors and school representatives, submit permit application, 60 Day Review Period
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.
Four visits per year for site maintenance | Remove trash, debris, check signage.
Annual RF testing | 2-4 visits per year for carrier modifications.
With over 20 years experience, Milestone Towers is the leading developer of wireless infrastructure and cell towers in partnership with school, government and utility landowners.